Budget tracking
Cost structure and cost breakdown exactly as estimated – plus ongoing plan-vs-actual tracking. When estimating and control follow the same structure, every deviation can be traced to its cause.
Not the actual position, but a reliable forecast of final cost – continuously updated while corrective action can still make a difference.
As soon as an order is placed, the budget is committed in economic terms – even if the invoice arrives months later.
That is exactly the task: we record open orders and commitments entered into – the commitments – from the moment they arise. Together with the actual costs incurred and the work still to be awarded, they form the basis for the forecast of final cost, the Estimate at Completion (EAC). This is the figure a project leadership uses to steer the actual cost development and respond early to deviations.
We take the cost structure from Cost Estimating – estimating and control follow the same logic. Closely linked to cost are Project Scheduling and Document Control; if you need all three together and at the right scale, you will find them in Project Controls on demand.
Cost control as a discipline of project control – from the structure to the report.
Cost structure and cost breakdown exactly as estimated – plus ongoing plan-vs-actual tracking. When estimating and control follow the same structure, every deviation can be traced to its cause.
We record open orders and commitments entered into from the moment they arise. That way the committed capital is visible long before the invoice arrives.
A reliable forecast of total cost at project completion, continuously updated, with trend analysis and scenarios for the cases that can realistically occur.
Plan-vs-actual comparisons with the cause identified – the basis for corrective action that targets the right point.
For every change and every variation, we show the impact on budget and final cost. That keeps visible what a decision really costs.
Cost reports for project leadership, steering committee and specialist departments, each suited to its audience – from one shared data basis, with deviations, their causes and the current forecast.
The forecast depends on regularity: only when it is recalculated in every cycle does it become a reliable management tool.
We take the cost structure from the estimate and align budget, cost breakdown and reporting rhythm with it. That way estimating and control follow the same logic, and plan and actual remain comparable at all times.
Actual costs, open orders and commitments entered into are recorded continuously. The commitments are the most important figure: they show what is already committed but not yet paid.
From actual costs, commitments, trend and outstanding work, we regularly project the final cost. The forecast shows the realistic position, even when it is uncomfortable – only then is it a reliable basis for the project leadership's decisions.
The forecast, with the causes of deviations and proposals for corrective action, goes first to the project leadership, then to the steering committee. For agreed measures, we follow up until their effect is visible in the cost forecast.
Three situations – what they share is the question of what the project will cost in the end.
Cost control needs a budget to steer against, and schedule control that shows when costs will be incurred.
Cost estimates and budget reviews with transparent, documented assumptions.
More on Cost Estimating & BudgetPlanning and scheduling for capital projects, from the idea to commissioning.
More on Project SchedulingScheduling, Cost Control and Document Control for capital projects – flexibly scalable from 0.1 FTE.
More on Project Controls on demandWe support capital projects in these industries:
Accounting records what has been invoiced – that is its job, and it does it precisely. Cost control looks ahead: it also tracks open orders and commitments, projects the final cost from them and reports variances while the course can still be corrected. Together, the two give the complete commercial picture.
Commitments are the capital that is already tied up even though no invoice has arrived yet: purchase orders placed, services contracted and obligations entered into. For equipment with long lead times, many months often pass between order and invoice. If you record commitments, you know the real cost position at the time of ordering – not only at the time of payment. Services not yet contracted are not included; they go into the forecast of final cost as planned costs.
Estimate at Completion – the forecast of total cost at the end of the project. It is recalculated in every reporting cycle from actual costs, commitments, trends and the work still outstanding. This shows a variance early, while there is still time to take corrective action. The actuals show what has been spent so far; the EAC shows what total cost to expect at the end.
Yes. We work in your systems or bring proven templates if there is no structure in place yet. What matters is not the tool anyway, but the discipline of a regular, honest forecast.
From as little as 0.1 FTE – so also for projects where a dedicated full-time position would not pay off. We work out the actual scope together, based on your project. Through Project Controls on demand, it can be arranged flexibly and adjusted to your needs at any time.
We charge by the hour, by day rates or at a fixed price – we work out together which model fits. The effort depends on the size of the project, the reporting frequency and the number of contract packages. For a first indication, the project volume and duration are enough for us. The initial call is free of charge.
Terms such as Cost Control and Earned Value are explained in our glossary – along with 57 other terms from the turnaround and project business.
Further reading: an article by our specialists on this topic.
Many smaller projects run without cost and schedule control because a full post per discipline is not worth it. It also works at a smaller scale: from 0.1 FTE.