Turnarounds · TAR-Check How ready is your turnaround really?

According to industry studies, around 90% of all shutdowns miss at least one of their targets – and it is almost always decided long before the first spade goes in.

Six questions, two minutes, an honest result – no sign-up.

16
Analysis elements
3 days
on site
2 weeks
through to the result
Fixed price
on request – you know the cost in advance
The full TAR-Check

16 analysis elements. One maturity level.

The TAR-Check assesses your TAR processes across 16 analysis elements – and shows the maturity level of your organisation in a neutral comparison with your industry and with good/best practice. The benchmarking is based on objective criteria, developed from the data, facts and experience of hundreds of projects.

The 16 analysis elements in detail

  1. 01Strategy & tactics
  2. 02Organisation
  3. 03Administration & processes
  4. 04Purchasing & procurement
  5. 05Contracts
  6. 06Expenditure & cost
  7. 07Communication
  8. 08Employee satisfaction
  9. 09HSE
  10. 10QA/QC
  11. 11Scope Development & Control
  12. 12Work planning
  13. 13Capital projects / TAR integration
  14. 14Manpower, logistics, infrastructure
  15. 15Operations
  16. 16Lessons Learned

For each element you receive an assessment with recommendations for action – matched to your maturity level. We do not leave you alone with the result: we help with implementation straight away, in an advisory and operational role. The result shows where to start: for example in scope management, in Turnaround Scheduling or in leading the shutdown itself.

20406080100Strategy & tacticsOrganisationAdministration& processesHSEEmployeesatisfactionCommunicationLessons LearnedCapital projects /TAR integrationOperationsWork planningQA/QCScope Development& ControlPurchasing &procurementExpenditure &costContractsManpower, logistics,infrastructure12398716131512101146514
Swipe sideways to view →The numbers match the list of the 16 elements above.

The results chart shows the self-assessment, the ep-cm assessment and the industry benchmark in one picture. Example chart – values for illustration only.

Self-test

Six questions. Two minutes. An honest result.

A short version of the self-assessment – it does not replace an analysis, but in two minutes it shows where your preparation stands.

Question 1 of 6

How many months before the shutdown is your scope freeze date?

The freeze date decides whether planning leads – or lags behind.

The quick check is a short version of the self-assessment and does not replace an analysis. Your answers stay in your browser – they are neither stored nor transmitted.

How the TAR-Check works

Only 3 days on site – results in two weeks

  1. 01

    Self-assessment & review

    First your turnaround team assesses itself, then comes the review with ep-cm specialists – only three days on site with you, with or without an upcoming turnaround.

  2. 02

    Benchmarking

    The results for each analysis element are benchmarked against your industry and compared with good/best practice – based on data from hundreds of projects.

  3. 03

    Recommendations

    Targeted recommendations for all 16 analysis elements, matched to your stage of development – presented to your management within two weeks. We help with implementation straight away, as advisers and hands-on.

If your concern is specifically the quality of your schedule, the SMI – Schedule Mechanics & Integrity Review complements the TAR-Check. The SMI checks your schedule against 35 criteria, and the results are available in 2–4 days.

Context

The TAR-Check provides the foundation

Working with ep-cm starts with a conversation. Then we come on site – with specialists from exactly the area concerned. The TAR-Check is the tool we use to measure rather than estimate. It is not a must: we also start work without it. But it lays the best foundation for everything that follows – for an improvement programme as well as for leading your next shutdown through Turnaround Management.

How working together begins
TAR-Check · SMI · DICTUM

Which tool do you need?

Three tools developed in-house, each with a different focus: the TAR-Check assesses the entire turnaround organisation, the SMI the quality of a specific schedule, and DICTUM forecasts cost, time and resources in the early phase of a project. Available individually or in combination.

Best practiceYour organisation

TAR-Checkthis page

What is assessed?
The entire turnaround organisation
Basis of assessment
16 analysis elements, benchmarking against industry & best practice
Result in
2 weeks (3 days on site)
Answers the question
“How well set up is our TAR organisation?”
Ideal for
Assessment of the TAR organisation – at any time; before a turnaround, ahead of the readiness gates
lowhigh

SMI

Schedule Mechanics & Integrity Review

What is assessed?
The technical quality & integrity of a schedule
Basis of assessment
35 criteria based on the 14 DCMA checks
Result in
2–4 days
Answers the question
“How reliable is this schedule – including that of our contractors and partners?”
Ideal for
Quality assurance of schedules before approval or award
SMI in detail
Early phasetoday

DICTUM

AI benchmarking & forecasting

What is assessed?
Cost, time & resources of a capital project (forecast)
Basis of assessment
Three industry benchmark databases + AI algorithms
Result in
Reliable forecast from FEL 2 (±10%)
Answers the question
“What will the project really cost – and how long will it take?”
Ideal for
Investment decisions in the early phase (FEL)
DICTUM in detail

Swipe sideways for the comparison →

Related services

What comes after the analysis

The TAR-Check tells you where you stand – and we do not leave you alone with the results. We help with implementation straight away, as advisers and hands-on. These three services start where the analysis most often reveals gaps.

Turnaround Management

The leading role in the turnaround – from definition through to closeout and lessons learned, as the operator's extended arm.

More on Turnaround Management

Advisory & Consulting

Strategy, organisation and processes for your shutdown – from the TAR philosophy to the improvement programme.

More on Advisory & Consulting

Scope Management

Capture, assess, freeze, control: the work scope is fixed – and holds even when the pressure rises.

More on Scope Management
Frequently asked questions

Questions answered

What does the TAR-Check cost?

The TAR-Check is a clearly defined package with a defined result. Billing is by the hour, by day rates or at a fixed price – we work out together which model fits. The amount depends on the size of your organisation and the timing – after the free initial call you receive a binding quotation.

How long does the TAR-Check take?

After your team’s self-assessment, we are on site with you for just three days – you receive the full results with benchmarking and recommendations for action within two weeks.

When is the right time for a TAR-Check?

Any time is a good time: a turnaround organisation can always improve, even between two shutdowns. If a specific turnaround is coming up, we recommend the TAR-Check before the key readiness gates – then the results feed directly into the decision at the gate.

What distinguishes the TAR-Check from other analysis methods?

The questions come from practice, not theory – asked by specialists who plan and carry out turnarounds themselves. Each group in the team gets targeted questions on its own topics, rather than only management being asked. This way, the team checks management’s statements and vice versa: you get a differentiated picture for each analysis element, and all levels of the hierarchy are brought up to the same level of knowledge.

Do we need finished planning documents for this?

No. The check assesses the status as it is – gaps are a result too. What is needed is your turnaround team's self-assessment and time for the joint review; it works with or without an upcoming turnaround.

Terms such as TAR organisation, readiness gate and self-assessment are explained in our glossary – along with 56 other terms from the shutdown and project business.